Using report scheduler
Issue 3 July 2001
59Send feedback: document@avaya.com
reports
Changing scheduled reports
It is easy to reschedule the time and day a report prints. As an
example, lets change the time on job ID 12 so that it prints at
10:00 p.m. (22:00).
To change the report scheduler for job ID 12:
1. Type
list report-scheduler and press RETURN.
The Report Scheduler screen appears.
2. Locate the job ID for the report you want to change.
In our example the job ID is 12.
3. Type
change report-scheduler 12 and press RETURN.
The Report Scheduler screen appears.
4. In the Print Time field, type
22:00.
5. Press
ENTER to save your changes.